- Under Section 510.1 of the 2021 International Fire Code from the International Code Council, a new building can skip an in-building radio system only where the fire code official determines the system is not needed, which fits when outside public safety signals already reach every floor at code-compliant levels.
- Whether you qualify depends on the code edition and local amendments your jurisdiction enforces, since the Automatic Fire Alarm Association summarizes the 2024 edition as keeping only the wired-system and automatically-activated-system exceptions, and places such as Oklahoma and Edmond add building-size triggers or third-party inspections.
- The fire code official needs a signed grid test report showing inbound and outbound signals of at least -95 dBm for analog or -100 dBm for digital under NFPA 1225, unless the frequency license holder and the AHJ specify other values, plus a delivered audio quality of 3.0 and pass rates of 95% of general areas under the 2021 IFC (90% where NFPA 1225 is referenced) and 99% of critical areas.
- A firefighter walking the floors with a portable radio does not count, because local rules such as the City of Maple Grove guide make the owner responsible for formal testing signed by someone holding a current FCC license, an APCO or PCIA technician certification, or a professional engineer license in radio engineering, or as otherwise approved by the fire code official.
- Run a baseline coverage test before filing, because the Santa Cruz Fire Department says plan review can take up to 15 working days, so a request without test data could cost up to three weeks, and a denial means you must design, install, and test a system under Section 510.1 or Section 510.2.
Someone on your project team says fire department radios already reach every floor, so you're wondering whether you can skip installing an emergency responder radio coverage system (ERRCS) before committing the budget. An ERRCS is an in-building network of antennas and signal boosters that keeps first responder radios working inside a structure. A waiver request filed without formal test data can burn weeks on the local reviewer's clock and leave you less time to install hardware if you're turned down.
Yes, you can get an ERRCS exemption in the United States if existing public safety radio signals already meet the fire code's coverage thresholds inside your building. Whether you qualify depends on the code edition and local amendments your city enforces, and on whether a credentialed technician tests and confirms adequate signal strength and voice clarity on every floor.
What the IFC 510.1 exceptions allow
You can skip installing an in-building radio system under the 2021 International Fire Code (IFC) only when the local fire code official determines that existing coverage makes the hardware unnecessary. In the United States, the International Code Council sets the baseline rules in IFC Section 510.1, which lists three exceptions for new buildings in the 2021 edition, and the second is the one you'd rely on when responder radios already work inside.
The authority having jurisdiction (AHJ), the local fire or building department responsible for code compliance, enforces the requirement through its fire code official. While the National Fire Protection Association's NFPA 72 and IFC 510 govern how public safety communications systems are supervised and tested, the exemption itself comes straight from the fire code's exceptions list. Under the 2021 code, as adopted in the 2021 Massachusetts Fire Code, all new buildings must have approved in-building, two-way coverage unless they meet one of three exceptions:
- A wired communication system under Section 907.2.13.2 is permitted in place of radio coverage when both the building official and the fire code official approve it, which does not help an owner relying on over-the-air radio signals.
- The building is exempt
where it is determined by the fire code official that the radio coverage system is not needed.
You use this exception when outside public safety radio signals already reach every floor at code-compliant levels. - If an active radio system could negatively affect the facility's normal operations, the fire code official can accept an automatically activated system instead, which changes how the equipment runs rather than waiving it.
Your city may be on the 2024 edition instead, and that changes the list. According to a 2024 model code summary from the Automatic Fire Alarm Association, the 2024 edition of Section 510.1 renames the system an emergency responder communication coverage enhancement system (ERCES) and keeps only the wired-system and automatically-activated-system exceptions in the baseline list.
Where your city's amendments change the answer
Your state or city may rewrite the model code to add building-size triggers, shift the burden of proof, or require third-party verification before the fire code official grants a waiver. Because code changes affecting BDA and DAS installations happen at both the state and municipal levels, your request has to satisfy the specific exception text your local government adopted. Two states show how local rules reshape the baseline model code:
- North Dakota amends the 2021 model code in the 2021 North Dakota Fire Code so that new buildings need in-building coverage only where required by the fire code official, tying the mandate to the official's determination from the start.
- Oklahoma modifies the 2024 code in its Oklahoma Uniform Building Code Commission 2024 IFC rules to let the fire code official require a third-party inspection by an approved agency to ensure adequate radio coverage is present. At the city level, Edmond, Oklahoma amends the same section to require a system only in buildings more than three stories above grade plane, with 50,000 square feet or more in combined floor area, with a total basement area of 5,000 square feet or more, or with more than one story below grade plane, while authorizing a third-party inspection when a new building will not install a system.
The evidence an exemption request needs
To convince the fire code official that a system is not needed, you have to submit a signed coverage test report from a qualified technician proving that existing public safety signals already meet every floor-area, signal-strength, and audio-quality threshold required for an ERRCS acceptance test.
The grid test at the adopted thresholds
Your building has to show clear two-way signal across nearly all of each floor, and the bar is higher in critical areas. A grid test is a floor-by-floor radio survey that divides each level into equal test squares and measures both incoming and outgoing signal performance in each square.
In jurisdictions on the 2021 IFC, such as North Dakota, 95% of general building areas and 99% of critical areas designated by the fire code official on each floor must meet the signal criteria. Where a jurisdiction references NFPA 1225, as California's Cosumnes Community Services District does, general floor areas must meet a 90% pass rate while critical areas stay at 99%.
Each grid measurement checks signal power in decibels relative to one milliwatt (dBm), a logarithmic scale where numbers closer to zero mean stronger radio signals, so -90 dBm is stronger than -95 dBm. Under the 2021 IFC rules reflected in the 2021 Colorado Fire Code, inbound signal strength must be at least -95 dBm throughout the coverage area.
Under NFPA 1225 criteria, both inbound downlink and outbound uplink signals must measure at least -95 dBm for analog systems and -100 dBm for digital systems, unless the frequency license holder and the AHJ specify other minimum values.
Strong signal alone won't pass a grid. Both the inbound and outbound channels must also hit a minimum delivered audio quality (DAQ) of 3.0, which scores how clearly a human voice comes through over the radio channel, or an equivalent signal-to-interference-plus-noise ratio (SINR). The NFPA Technical Committee on Public Emergency Service Communications defines DAQ 3.0 as speech understandable with slight effort that requires occasional repetition due to noise or distortion, and DAQ 3.4 as speech understandable without repetition despite some noise or distortion.
You might assume a firefighter walking the floors with a portable radio and giving a thumbs-up is enough to waive the system. It isn't. Local rules like Minnesota's City of Maple Grove radio coverage guide make it the building owner's responsibility to formally test regional radio system performance against floor-area and critical-area thresholds, with or without an in-building system.
Floor plans and the test record
Your tester should package the survey into a formal compliance report for the fire code official. The 2024 Montana Fire Code, for instance, requires a report after testing an installed system to verify compliance with Section 510.5.4. Your floor plans and the grid-by-grid measurements for general and critical areas on every level belong in that record, signed by a technician who holds the required licensing or certification.
The written AHJ determination
When your test report shows the building passes, the fire code official can determine that emergency responder radio coverage equipment isn't needed for the structure. Nevada's City of Reno 2024 IFC amendments say exactly that for existing buildings, so it's one city's example of how the decision gets made.
What a baseline assessment shows before you apply
Running a baseline coverage test before you file tells you whether your building's inbound and outbound dBm levels and DAQ scores hit the general and critical area pass rates, so you know whether to apply for an exemption or budget for an ERRCS. That answer protects your construction schedule. The Santa Cruz Fire Department in California, for example, says its plan review turnaround is up to 15 working days, so a request filed without test data could cost you up to three weeks just to get rejected.
Expect the AHJ to look at who ran the test. Maple Grove, for example, requires tests to be conducted, documented, and signed by someone holding a current Federal Communications Commission (FCC) license, a technician certification from the Association of Public-Safety Communications Officials (APCO) or the Personal Communications Industry Association (PCIA), or a professional engineer license in radio engineering, or as otherwise approved by the fire code official.
At Resolution Wireless, our ERRCS compliance services start with initial code research, frequency coordination, and pre-testing that captures the grid-level data an informal radio check misses. If your floors pass, you have the signed report you need to request a waiver. If coverage falls short, we handle the system design, installation, and final certification. You can also book a discovery call on our online calendar to talk through your property's wireless requirements with a wireless solutions expert.
What happens when the request is denied
If the fire code official denies your exemption request because the existing signal falls short, you have to design, install, and test an approved in-building radio coverage system to meet the new-building mandate under Section 510.1 or the existing-building triggers under Section 510.2 and Chapter 11. If a baseline test fails, move straight into budgeting, starting with the cost drivers in an ERRCS project, so you don't delay your certificate of occupancy.
Installing a system doesn't end the work at acceptance. Under the 2024 code rules adopted in Montana, the building owner or authorized agent must have an in-building system inspected and tested annually and whenever structural changes like additions or remodels could materially change the original field performance tests. Whether a granted exemption gets revisited after a remodel is a question for your AHJ. If a failed test or a renovation leaves your floors short of the code thresholds, Resolution Wireless designs, installs, and certifies the ERRCS hardware to get your building approved.
Speak to an expert at Resolution Wireless about your ERRCS coverage test
Filing an exemption request without grid test data can cost you weeks of fire department review time and still leave you without the proof the fire code official requires. You can get an exemption under the IFC 510.1 exceptions if outside public safety radio signals already reach inside your building. A credentialed technician's grid test shows it: at least -95 dBm for analog or -100 dBm for digital signals, a DAQ of 3.0, and 90% to 95% of general floor areas (depending on the standard your city adopted) and 99% of critical areas passing. The signed report gives you the fire code official's determination that you don't need a system.
If you're deciding whether to apply for a waiver or budget for hardware before you've tested coverage or filed with the AHJ, find out what your signal looks like first. Schedule a baseline ERRCS coverage assessment with Resolution Wireless, and we'll coordinate your local frequencies, test every floor against your city's adopted thresholds, and show you whether your building meets the thresholds an exemption request has to prove.