The 5 Most Common Reasons for ERRCS Change Orders (And How to Prevent Them)

Posted By: Resolution Wireless Staff Posted On: April 21, 2025 Share:

Contractors and developers operate under immense pressure to deliver projects on time and within budget. Few things can derail a project's schedule and finances faster than unexpected change orders. These modifications can introduce delays and friction, especially when dealing with life-safety systems.

An Emergency Responder Radio Communications System (ERRCS) is an in-building network that ensures first responders can maintain reliable communication during an emergency. It's often a non-negotiable requirement for obtaining a Certificate of Occupancy. Keep reading to learn about the most common reasons for these changes and how to avoid them.

woman in protective workwear and construction work 2024 09 23 02 10 16 utc

What Are Change Orders and Why Are They a Challenge for ERRCS Projects?

In construction, a change order is a formal document that amends the original contract to reflect an alteration in the scope of work. This could involve adding, removing, or changing services, materials, or timelines. While sometimes necessary, change orders often introduce significant challenges to a project's flow and financial stability.

The negative consequences can be substantial. Research shows that change order costs can account for 10 to 15 percent of a total contract's value, creating serious budget overruns. A high frequency of changes can also disrupt workflow and reduce a project team's productivity by as much as 30 percent.

ERRCS installations are particularly prone to these issues. Their technical complexity, reliance on unpredictable radio frequency (RF) signals within buildings, and the direct oversight of the Authority Having Jurisdiction (AHJ) create a unique set of variables. If not managed proactively, these factors can easily lead to unforeseen modifications and expensive delays.

The Top 5 Reasons for ERRCS Change Orders

While every construction project has its own unique challenges, most ERRCS change orders don't come out of the blue. They typically stem from a handful of recurring issues that arise during the planning, design, and coordination phases. Understanding these common pitfalls is an important step in proactive project management and effective risk mitigation.

Inaccurate or Incomplete RF Signal Survey

The entire ERRCS design is built upon a foundational element known as the "donor signal." This is the external signal from the public safety radio tower that the in-building system will amplify and distribute. The strength and quality of this signal are fundamental to the system's performance, and one of the biggest mistakes a project can make is not conducting a professional survey before work begins.

If an inadequate donor signal is discovered late in the process, it can trigger a major change order. The system may suddenly require a powerful and expensive Bi-Directional Amplifier (BDA) that wasn't included in the original budget. To meet codes like NFPA 1225, which mandates a minimum signal strength of -95 dBm and requires 99% coverage in critical areas and 90% in general areas, this equipment becomes non-negotiable.

Prevention starts with commissioning a comprehensive RF signal survey before the system is designed or bid on. A thorough survey involves more than a simple strength test. It includes analyzing signal quality and testing multiple potential donor sites on the property to identify the most reliable source for the ERRCS.

Evolving or Misinterpreted AHJ Requirements

The Authority Having Jurisdiction, usually the local fire marshal, has the final say in approving an ERRCS installation. This official ensures the system complies with national codes like the National Fire Protection Association (NFPA) and the International Fire Code (IFC). However, many jurisdictions have specific local amendments or interpretations of these codes.

A change in fire marshal, a new local ordinance, or a simple misinterpretation of a requirement can lead to unexpected demands. For instance, while the IFC may specify a 12-hour battery backup, a local AHJ in a high-risk hurricane zone might amend this to require a 24-hour backup, triggering a significant change order if not accounted for in the initial design. These changes might also include additional system monitoring alarms or revised antenna placement.

The best way to prevent this is through early, direct, and documented communication with the local AHJ. Your ERRCS vendor should be involved in these pre-construction meetings to ask the right technical questions. Getting all specific requirements, from coverage levels to testing protocols, confirmed in writing before finalizing the design is key to avoiding last-minute surprises.

Poor Design and Coordination With Other Trades

An ERRCS doesn't exist in a vacuum. It must be integrated into a building's complex web of mechanical, electrical, and plumbing (MEP) systems. Poor coordination between the ERRCS installer and other trades is a frequent source of conflict and change orders, with common issues including antenna pathways clashing with HVAC ductwork, plumbing lines, or large electrical conduits.

Another frequent problem is the failure to allocate sufficient space and dedicated power for ERRCS equipment in electrical or IT rooms. When these conflicts are discovered during installation, the cost to reroute infrastructure can be significant. For example, installing cabling for system components out of sequence can be up to six times more expensive than doing it correctly during the initial construction phase.

To prevent these issues, it’s best to use an integrated design process. The ERRCS specialist should coordinate directly with the project’s MEP engineers from the very beginning. Incorporating the ERRCS layout into the project’s Building Information Modeling (BIM) allows the team to identify and resolve clashes virtually before they become expensive problems in the field.

Unforeseen Structural and Material Obstacles

Modern buildings are increasingly constructed with energy-efficient materials that can create major problems for radio signals. Materials like concrete with steel rebar, metal roofing, certain types of insulation, and especially Low-E (low-emissivity) glass can severely block or degrade RF signals. Low-E glass, for instance, can increase a building's "no coverage" area from 47% to 79% in certain simulations.

When these materials aren't accounted for in the initial design, the installed system may fail to meet the required coverage levels. This forces a change order to add more antennas, increase amplifier power, or even redesign parts of the system to overcome the unexpected signal loss. The cost and delays associated with these retrofits can be substantial.

This problem is preventable if the ERRCS vendor reviews the full architectural drawings and material specifications during the design phase. A qualified expert can identify signal-attenuating materials and calculate their likely impact on RF propagation. This allows them to plan the system coverage and component placement accurately from the start, ensuring the design is robust enough for the building's actual construction.

Scope Gaps in the Original Bid and Specifications

Scope gaps happen when the initial Request for Proposal (RFP) or bid documents are vague or missing key details. This lack of clarity can lead to vendors submitting bids based on different assumptions about what is required for a complete and compliant system. As a result, the selected bid may not include everything needed for final AHJ approval.

Common examples of scope gaps include failing to specify requirements for pathway survivability, which protects cables from fire. Others include not mandating plenum-rated cabling for use in air-handling spaces or neglecting to define the scope for system monitoring alarms and final acceptance testing procedures. When these necessary elements are added later, they become costly change orders.

The most effective prevention strategy is to develop a detailed ERRCS performance specification before seeking bids. This document should clearly outline all project requirements, from signal strength criteria and coverage maps to testing protocols and AHJ sign-off processes. Providing this level of detail ensures all vendors are bidding on the exact same scope of work, eliminating ambiguity and protecting the budget.

Managing Unavoidable Change Orders

Even with the best planning, some change orders are unavoidable. When a change becomes necessary, managing it properly is important to control costs and minimize schedule disruptions. A structured process ensures that all stakeholders are aligned and that the project's budget remains under control.

The foundation of effective management is clear and timely documentation. Every change should be initiated with a formal Change Order Request that details the scope of the new work, the materials required, and the reason for the alteration. This document should include a complete breakdown of costs and an analysis of the potential impact on the project timeline.

This formal request should then move through a clearly defined approval process, ensuring the building owner, general contractor, and ERRCS vendor all sign off before work begins. Maintaining a comprehensive change order log that tracks the status of every request is also a good practice. This log creates a single source of truth for the project, preventing miscommunication and ensuring transparency from start to finish.

A Proactive Checklist for Preventing ERRCS Change Orders

A proactive approach focused on early engagement and detailed planning is the most effective strategy. Follow these steps to mitigate risk and protect your project budget:

  1. Engage an ERRCS Partner Early: Bring a qualified vendor into the project during initial planning to conduct a thorough RF donor signal survey and establish a baseline for the system design.
  2. Conduct an AHJ Pre-Construction Meeting: Schedule a meeting with the local Authority Having Jurisdiction, with your ERRCS vendor present, to confirm all specific requirements and get them in writing.
  3. Integrate with Project Designs: Ensure the ERRCS layout is fully incorporated into the project’s MEP plans, preferably within a shared Building Information Modeling (BIM) model, to identify and resolve clashes virtually before construction.
  4. Review All Material Specifications: Have your ERRCS expert review the full architectural drawings to identify signal-blocking materials like Low-E glass or reinforced concrete and adjust the system design accordingly.
  5. Develop a Detailed Performance Specification: Create a comprehensive specification document that outlines all project requirements before seeking bids. This ensures all vendors are bidding on the exact same scope of work, eliminating ambiguity.

Partner With an ERRCS Expert to Protect Your Project Budget

The majority of expensive ERRCS change orders aren't inevitable. They are typically the result of foreseeable issues in planning, communication, and design. Proactive management and early involvement from a qualified expert are the keys to keeping an ERRCS installation on schedule and on budget.

Investing in a proper plan from the start protects your project from the delays and cost overruns that can jeopardize a successful completion. Our turnkey approach at Resolution Wireless is specifically designed to identify and mitigate these risks from the outset, ensuring a smooth process from the initial survey to final AHJ approval.

If you want to protect your next project’s budget from ERRCS-related change orders, contact Resolution Wireless today. Our team of experienced professionals is here to provide a consultation and help you develop a clear path to a compliant and cost-effective installation.